The foundation is the part of the house your frame supplier will not build and your budget will not forgive. On an Irish rural site it is also the item most likely to move.
Start with the site investigation
Before any foundation decision, you need to know what is under the topsoil: soil type, bearing capacity, water table, and whether there is rock or peat. A site investigation is a small cost against the risk it removes, and your engineer cannot design without one. On a rural greenfield site it is not optional.
The three options
Insulated raft
A reinforced slab cast on a continuous layer of insulation. It is the natural partner for timber frame: no perimeter cold bridge, the floor and the foundation in one operation, and a flat, accurate surface to set the frame out on. Underfloor heating pipes go in before the pour.
- Good for: level or gently sloping sites with reasonable bearing
- Watch: every service penetration has to be set out before the pour — there is no second chance
- Best for: Part L performance, because the floor perimeter is where heat quietly leaves
Strip foundation with a suspended or ground-bearing floor
The traditional Irish approach. Works on slopes, tolerates variable ground, gives you a rising wall to level off. More operations, more cold bridge detail to resolve at the wall-floor junction.
Piles
Where bearing is poor — peat, made ground, deep soft strata — piles with a ground beam or a piled raft are the answer. Expensive, definitive, and decided by the engineer rather than by preference.
Tolerance: the part people miss
A factory-made panel is manufactured to the millimetre. It will not stretch to meet a foundation that is 30 mm out of square, and packing it out defeats the airtightness detail you paid for. Frame suppliers issue a setting-out drawing with a tolerance — typically far tighter than a blockwork build assumes — and the groundworks contractor has to be told about it before he prices, not after he pours.
Sequence
- Site investigation and engineer’s foundation design
- Frame supplier issues setting-out, loads and tolerances
- Groundworks, drainage and radon barrier
- Insulation, reinforcement, service ducts, UFH pipes
- Pour and cure
- Survey the finished slab and confirm it against the tolerance before the frame is delivered
That last step takes an hour and is skipped constantly. Do it.
Frequently asked questions
Which foundation is best for timber frame?
An insulated raft in most cases: it eliminates the perimeter cold bridge and gives the accurate, level base a factory frame needs. Ground conditions can override this.
Does the frame supplier design the foundation?
No. The supplier issues loads, setting-out and tolerances; your engineer designs the foundation for your ground conditions and a local contractor builds it.
What a Timber Frame Kit Actually Costs in Ireland in 2026
What is in a timber frame kit price, what is not, and how the kit figure relates to the full cost of building a one-off …
Cost to Build a One-Off House in Ireland in 2026: Where the Money Goes
A stage-by-stage breakdown of what a one-off house costs in Ireland in 2026 — groundworks, shell, services, finishes, fe…
IS 440 and Imported Timber Frame: What an Irish Self-Builder Must Check
If your timber frame is manufactured outside Ireland, this is the documentation your engineer, assigned certifier and le…
Catalogue with prices
Register for access to the full catalogue: every specification option with its price, a configurator with a running total and an offer within 30 days.


